Short answer: Before you pay more than a small booking amount, collect and verify the project’s RERA registration, the sanctioned plan, the title papers, the draft agreement for sale and the payment schedule. After signing, get the agreement registered, track construction on the RERA site, and at the end insist on the occupancy certificate and a registered conveyance deed. The steps are in order below, with the legal basis for each.

This is a procedure for buying a flat from a builder in a project that is under construction or newly completed. For a resale flat the same logic applies, with a few different documents, and we note these where it matters. Time limits and forms differ between states, so check the local rule where the guide says so.

Want the full picture? The Lexfolio Home Buyer’s Legal Course is a self-paced certificate course on the legal side of buying a home in India. Price: Rs 399.

Step 1: Confirm the project on the RERA website

  • Take the registration number from the advertisement or brochure. Section 11(2) of the RERA Act requires it, along with the Authority’s website address, in every advertisement.
  • Open your state RERA website, search by project name or number, and download the registration certificate, the proposed completion date and the sanctioned plan.
  • Note the promoter’s name and the land owner’s name. If they are different companies, you will need to see the agreement between them.
  • Check for complaints, orders or revocation notices against the promoter.

Projects with land up to 500 square metres or up to eight apartments are exempt from registration under section 3(2), and so are projects that already held a completion certificate when the Act began. For such projects you need to work harder on the other steps.

Step 2: Ask for the title and approval documents

DocumentWhy it matters
Title deeds of the land and the chain of earlier transfersShows that the seller or promoter has a right to build and sell
Encumbrance record for the land from the registration officeShows registered mortgages or transfers; the period covered and format vary by state
Sanctioned building plan and layout from the local development authority or municipal bodyConfirms the building is approved and shows floors, setbacks and common areas
Land use and zoning permissionConfirms that residential construction is allowed
Environmental and fire clearances, where applicableRequired for larger projects
Bank NOC or mortgage release, if the land or project has a loanThe bank may hold the title papers or have a charge over the land

A lawyer’s title report is worth paying for. The report should list every document examined, name any gaps and state clearly whether the lawyer considers the title marketable. For a resale flat, ask also for the earlier sale deeds or allotment papers, the society’s share certificate and no-objection letter, the latest maintenance and tax receipts, and the original loan closure papers if the seller had a home loan.

Step 3: Pay only the booking amount until the agreement is registered

Section 13(1) of the RERA Act prohibits a promoter from taking more than 10 per cent of the cost of the apartment as advance or application fee without first entering into a written agreement for sale and registering it. If the builder asks for more, ask for the agreement first. Pay through cheque or bank transfer, never in cash, and ask for a receipt for each payment.

Step 4: Read the draft agreement for sale before the signing day

Ask for the draft well before the signing date and read each clause. Section 13(2) says the agreement must contain the project particulars, the payment schedule, the date of possession and the rate of interest on default. Check the following.

  • Unit details: tower, floor, flat number, carpet area, parking and any exclusive terrace or balcony.
  • Price and payment plan: total price, taxes and what each instalment is linked to. Instalments should follow construction stages, not just dates.
  • Possession date and delay interest: the same rate of interest should apply to the promoter’s delay and to your late payment, as the Act intends (section 19(6) and 19(7) cover the buyer’s side).
  • Specifications and amenities: these should be the ones shown in the sanctioned plan and the brochure.
  • Cancellation clause: section 11(5) allows cancellation only as the agreement provides. A clause letting the builder cancel for trivial reasons is a red flag.
  • Changes: under section 14(2) the promoter cannot change sanctioned plans or specifications without the buyer’s consent, apart from minor changes on the advice of an architect or engineer with intimation to the buyer.

Step 5: Sign, pay stamp duty and register within four months

Registration is compulsory for the transfer of a right in immovable property worth Rs 100 or more under section 17 of the Registration Act, 1908. A document other than a will must be presented for registration within four months of execution (section 23). A further four months may be allowed in case of urgent necessity or unavoidable accident, on payment of a fine of up to ten times the registration fee (section 25). Stamp duty and registration charges are set by each state, so get the exact figure from the sub-registrar’s office or the state’s online system before the date. Both parties and two witnesses usually attend, and identity documents and photographs are required.

Step 6: Handle the tax and loan paperwork

  • If you are buying from a resident seller and the consideration or stamp duty value is Rs 50 lakh or more, you deduct tax at 1 per cent of the higher figure. For transactions from 1 April 2026 the provision is section 393(1) of the Income-tax Act, 2025 and the reporting form is Form 141. Confirm the current procedure with a chartered accountant.
  • If you are taking a home loan, the bank will ask for the same title papers and sanctioned plan. Do not treat the bank’s approval as a legal opinion in your favour: the bank checks its own security, not your interests.
  • Keep every receipt, demand letter and email from the builder in one file.

Step 7: Track construction and demand notices

Compare each demand letter with the payment schedule and the stage of construction. The promoter must update the Authority’s website every quarter under section 11(1), and 70 per cent of the money collected has to sit in a separate account for construction and land cost under section 4(2)(l)(D). If a demand does not match the stage reached, write to the builder and keep the reply.

Step 8: At the end, insist on the occupancy certificate and conveyance

  • Occupancy or completion certificate from the local authority. Do not take possession without asking for it.
  • Possession: section 19(10) requires the buyer to take physical possession within two months of the occupancy certificate.
  • Conveyance deed: unless local law sets a different period, section 17(1) requires the promoter to execute a registered conveyance deed within three months of the occupancy certificate, and 17(2) requires the necessary documents and plans to be handed over within 30 days.
  • Inspection: check the flat against the agreement. If a structural or other defect appears within five years of handover, you can ask for it to be fixed free of charge within 30 days under section 14(3), and claim compensation if it is not.
  • Association: section 11(4)(e) provides for the formation of an association of allottees in the absence of local laws, within three months of a majority of buyers having booked.

If something goes wrong

Delay in possession, failure to refund, false statements in advertisements and defects can be taken to the state RERA Authority by a complaint under section 31, and claims for compensation are decided by the adjudicating officer, who is expected to decide within 60 days under section 71. Under section 18(1) a buyer who chooses to leave a delayed project can claim a refund with interest, and a buyer who stays can claim interest for each month of delay. A consumer complaint is an alternative route, as the Supreme Court held in Imperia Structures v. Anil Patni (2020), and must be filed within two years of the cause of action under section 69 of the Consumer Protection Act, 2019, on the e-Jagriti portal. Send a written notice to the builder first and keep proof of delivery.

Printable checklist

  1. RERA registration certificate and project page saved.
  2. Title report from a lawyer, with the chain of documents.
  3. Sanctioned plan, layout and land use permission seen.
  4. No more than 10 per cent paid before a registered agreement.
  5. Draft agreement read; payment plan tied to stages; possession date and interest clauses checked.
  6. Stamp duty paid and agreement registered within four months.
  7. Tax deduction handled if the price is Rs 50 lakh or more.
  8. Occupancy certificate, possession letter and registered conveyance deed received.

Frequently asked questions

Which document proves that I am the owner of the flat?

In a sale, the registered sale deed or conveyance deed is the main proof of ownership. An allotment letter or an agreement for sale gives contractual rights but does not by itself complete the transfer.

Is it enough to rely on the bank’s legal opinion?

Not safely. The bank’s lawyer reports to the bank, for the bank’s security. A report for you should come from your own lawyer.

How much can the builder take before the agreement for sale is registered?

Not more than 10 per cent of the cost of the apartment under section 13(1) of the RERA Act.

What is the time limit to register the agreement?

A document must be presented for registration within four months of execution under section 23 of the Registration Act. A further period of up to four months is available only for urgent necessity or unavoidable accident, with a fine.

Do I need the occupancy certificate even if the builder says the flat is ready?

Yes. The Act ties the conveyance and the buyer’s duty to take possession to the occupancy certificate (sections 17 and 19(10)), so ask for it before taking possession.

Go beyond this guide. Continue with the Lexfolio Home Buyer’s Legal Course, a self-paced certificate course on the legal side of buying a home in India. Price: Rs 399.

This article is general information, not legal, tax or financial advice for a specific case. Laws, rules and fees change and differ by state, so check the current text or consult a lawyer for your situation. Lexfolio is a learning resource.

Useful books for this topic

As an Amazon Associate, Lexfolio earns from qualifying purchases. Prices and availability are shown on Amazon.

Free CLAT PG 2027 sample: exam guide + 2 judgment passages

Get our 16 page CLAT PG starter free: the 2027 pattern, how to read judgment passages fast, the 25 key Supreme Court judgments of 2026, and two practice passages with 10 explained questions. Plus new free guides and law updates by email. Unsubscribe any time.

Learn this properly, with a certificate. Police and FIRs, consumer and bank fraud complaints, property, wills and inheritance, work rights, family law, cyber fraud and RTI, in plain English. Certificate Course in Everyday Law for Every Indian, ₹349: self-paced lessons, module quizzes and a final test; pass at 60% for a verifiable Lexfolio certificate.

See all Lexfolio certificate courses

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *